Thank you for the opportunity to respond to your draft audit report entitled FDIC ‘s Consolidated
Facilities Management Approach. We appreciate the OIG for its acknowledgement that the
Consolidated Facilities Management (CFM) contract structure and the FDIC’s management of
the contract were generally adequate to ensure the efficient operation of the FDIC’s Washington,
D.C., area facilities.
Although the OIG identified efficiencies in the facilities operations, the report did include seven
recommendations. Six recommendations pertained to the Division of Administration (DOA)
while the one remaining recommendation was made to the Division of Finance (DOF) on the
appropriateness of costs that were expensed rather than being capitalized.
We have carefully reviewed the OIG’s report, considered each of your recommendations, and
have provided a detailed “Management Response” that includes planned corrective actions and
expected completion dates as appropriate. Also, we have included a section that provides
clarification to some of the report’s findings. We believe these comments are necessary to
provide a more balanced perspective. Our full response is provided below.
MANAGEMENT DECISION
Recommendation #1. That the Director, DOA, amend the APM to provide guidance on
contract bundling in accordance with statutory and regulatory requirements, including:
- Performing market research in support of contract bundling decisions.
- Maximizing participation of small business concerns in bundled contracts to include
identifying impediments to, and alternative strategies for, small business participation.
- Assessing whether proposed contract bundling will result in measurably substantial
benefits to the FDIC and is necessary and justified.
- Providing SBA the opportunity to review proposed contract bundling.
Management Response. DOA concurs with the recommendation. The DOA Acquisition
Services Branch (ASB) will amend the APM to include language on contract bundling using the
FAR implementation as a guideline. ASB will issue Interim Policy Guidance by May 15, 2006.
Recommendation #2. That the Director, DOA, amend the APM to require monitoring and
periodic assessments of whether intended benefits and small business participation are being
achieved in bundled contracts for use in procurement decisions.
Management Response. DOA agrees with the intent of the recommendation, but does not
concur with the specific recommendation to amend the APM. It is the on-going responsibility of
each program office to assess the progress and performance of various projects and make
determinations as to whether those projects are achieving their intended objectives. We do not
believe this issue is appropriate for inclusion in acquisition policy.
Recommendation #3. That the Director, DOA, prior to the next contract option period, perform
an assessment to determine if the CFM contract is achieving intended benefits, including small
business participation.
Management Response. DOA concurs with this recommendation. The DOA Corporate
Services Branch will assess whether the CFM contract is achieving intended benefits against
established benchmarks and will review the level of small business participation with the
Acquisition Services Branch. However, this review will not be completed prior to the exercise
of the next option due to time constraints. CSB expects to complete this review by June 30,
2006.
Recommendation #4. That the Director, DOF, identify and capitalize all the costs for the
column collar installation project.
Management Response. The Division of Finance (DOF) agrees with the recommendation that
all of the costs associated with the F Street Column Project should be capitalized. An asset for
the F Street Column Project was established in the Asset Management module in September
2005. The total cost associated with the F Street Column Project at that time was $843,438.00.
Based on a subsequent review of the invoices associated with the project by the DOA and DOF it
was determined that an additional $1,322,873.00 in costs should also be capitalized. The review
of invoices determined that the costs associated with the project which were not capitalized were
coded to the Miscellaneous Operating Expense account when the invoices were submitted to
DOF for payment. On March 15th an adjusting entry was recorded by DOF which increased the
amount of the F Street Column capitalized asset by $1,322,873.00.
DOF does not feel that the costs of the F Street Column Project which were not capitalized
should be reported as “Funds Put To Better Use”. The costs to be capitalized do not constitute a
reduction in outlays, unnecessary expenditures or any other specifically identified savings to the
Corporation, in relation to the project. Furthermore, the designation of “funds put to better use,”
as applied, does not fall within one of the six actions identified in the Inspector General Act. [ 1 ]
Recommendation #5. That the Director, DOA, amend the APM to establish requirements
associated with documented market research and justification of noncompetitive procurements
for large-dollar-value work orders on existing contracts.
Management Response. DOA agrees with the intent of the recommendation, but does not
concur with the specific recommendation to amend the APM. The APM currently contains
language in Chapter 2, Paragraphs 2.J.1 and 2.J.2 that require market research and justifications
of noncompetitive procurements when the value of the procurement is greater than $100,000.
This language would apply to any work outside of the scope of the original contract.
The large dollar work order reviewed under this audit was determined to be within the scope of
the contract by the contracting officer. Since the contract made provisions for work orders to be
written against the contract, the contracting officer determined that writing the work order was
within the original scope of the contract and did not require a justification. This decision was
consistent with the contract and with acquisition guidance, and was within the scope of the
contracting officer’s authority.
Recommendation #6. That the Director, DOA, amend the APM to provide guidance on
structuring incentive fee provisions, including clearly establishing the performance standard and
service that are considered above and below standard.
Management Response. DOA agrees with the intent of the recommendation, but does not
concur with the specific recommendation to amend the APM. Incentive structures for specific
requirements are highly unique and based upon project needs. Prescriptive policies as to how to
structure incentives would not be appropriate. Since the award of the CFM contract, DOA/ASB
has addressed the need for increased understanding of performance based contracts by providing
training to the contract specialists on performance based contracting, incentives and performance
management. For example, in 2004, a class was presented on-site for ASB contract specialists.
In order to improve contract specialist and project manager access to available information on
this topic, we will modify the DOA website for “Procuring Goods and Services” to establish
links to guidance and best practice information from sources such as the Office of Federal
Procurement Policy. These links were added to the website on March 16, 2006.
Recommendation #7. That the Director, DOA, seek modification of the incentive fee
provisions in the CFM contract to provide specific performance targets that must be exceeded to
earn incentive fees.
Management Response. DOA does not concur with this recommendation. The next option
must be exercised on April 1. Although it might be possible to improve the incentive structure of
the current contract, DOA does not believe the current structure harms the FDIC. An attempt to
renegotiate the incentive provisions while attempting to exercise the next option would not be
appropriate and could result in a break in service of the current contract. Based on current
utilization rates, the contract ceiling is estimated to be reached by the first quarter of 2007 and
market research for a new contract will be initiated in the near future. DOA will consider the
input of this OIG report as we formulate the acquisition strategy for the follow-on contract.
If you have any questions regarding the response, our point of contact for this matter is Andrew
Nickle, Audit Liaison for the Division of Administration. Mr. Nickle can be reached at (703)
562-2126.
| cc: | James H. Angel, Jr., OERM |
| | Glen Bjorklund, DOA |
| | Ann Bridges Steely, DOA ASB |
| | Michael J. Rubino, DOA CSB |