Figure 2: Project Integration Timeline

Month XBAT Contract CDR Solicitation
July 2002   Request for Proposal Issued 7/31/02.
August 2002

ASB Advanced Authorization Letter signed 8/09/02.

Not to exceed: $131,733

Amendment to the RFP - August 2002.
September 2002

Draft Functional Requirement Document 9/11/02

XBAT BOA w/SOW, effective 8/09/02, signed 9/25/02

System Development estimated at $395,000

Amendment to the RFP - September 2002.
October 2002

Draft Functional Requirementsw Document (Revision 10) 10/16/02

Task Assignment #1 Signed 10/17/02

Task Assignment #2, Signed 10/17/02 - Waived certain functional requirements.

Proposals received - 10/07/02.

Amendment to the RFP - October 2002.

CDR Request for Quote and Quality & Assurance Responses, promising a fully functioning XBAT meeting the 9/02 and 10/02 FRDs.

December 2002

Task Order #1 - Signed 12/16/02, effective 8/09/02

Canceled and ratified task assignments #1 & #2.

System development increased to $712,000.

 
January 2003  

Best and Final Offers Received from XBAT Contractor and CDR Winning Bidder - January 2003.

Source: OIG Analysis of XBAT and CDR Files